Question
1 Approved Answer
Fill in the blanks in the following cost control table. Budget Amounts Commitment Incurred- This Period Incurred- To date Forecast No. Work Package Approved Original
Fill in the blanks in the following cost control table. Budget Amounts Commitment Incurred- This Period Incurred- To date Forecast No. Work Package Approved Original Changes Current Budget Original Approved Changes Current Planned Incurred Planned Incurred ETC EAC General IP- Site and 01 Buildings Cleanup 80,000 25,000 80,000 25,000 40,000 35,000 40,000 35,000 75,000 Buildings, IP- Equipment 840,000 03 and Systems 840,000 400,000 400,000 210.000 685,000