Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

* Five batch jobs, A through E, arrive at a computer center at essentially the same time. They have an estimated running time of 15,

* Five batch jobs, A through E, arrive at a computer center at essentially the same time. They have an estimated running time of 15, 9, 3, 6, and 12 minutes, respectively. Their (externally defined) priorities are 6, 3, 7, 9, and 4 respectively, with a lower value corresponding to a higher priority. For each of the following scheduling algorithms, determine the turnaround time for each process and the average turnaround for all jobs. Ignore process switching overhead. Explain how you arrived at your answers. In the last three cases, assume that only one job at a time runs until it finishes and that all jobs are completely processor bound.

a.) round robin with a time quantum of 1 minute

b.)priority scheduling

c.) FCFS (run in order 15, 9, 3, 6, and 12)

d.) shortest job first

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Relational Database Design A Practical Approach

Authors: Marilyn Campbell

1st Edition

1587193175, 978-1587193170

More Books

Students also viewed these Databases questions

Question

What is the growth rate of GDP per capita?

Answered: 1 week ago