Question

1 Approved Answer

Flag question: Question 6 Question 64 pts In which document would the work package be identified? Group of answer choices The project charter The team

Flag question: Question 6Question 64 pts

In which document would the work package be identified?

Group of answer choices

The project charter

The team charter

The WBS

The statement of work

Flag question: Question 7Question 74 pts

Three-point estimating that includes a weighted value of four times the most likely is called

Group of answer choices

Beta distribution

A triangular estimate

A PERT estimate

Both beta distribution and a triangular estimate

Flag question: Question 8Question 84 pts

Which of the following is hierarchical deconstruction of the work?

Group of answer choices

The project charter

The scope management plan

The work breakdown structure

The configuration management plan

Flag question: Question 9Question 94 pts

During which meeting will the development team and the stakeholders focus on what they are building?

Group of answer choices

The Daily Standup

The Sprint Planning meeting

The Sprint Review

The Sprint Retrospective

Flag question: Question 10Question 104 pts

A ______________ is the process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.

A blank is the process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.

Group of answer choices

Statement of work

Project charter flow diagram

Project charter

Project management plan

Flag question: Question 11Question 114 pts

Which of the following is not part of the project plan?

Group of answer choices

The project charter

The scope management plan

The HR management plan

The configuration management plan

Flag question: Question 12Question 124 pts

A product backlog should prioritize the user stories by

Group of answer choices

Easiest to get done

Highest business value

Least expensive

Results of the nominal group technique

Flag question: Question 13Question 134 pts

The _____________ establishes a partnership between the performing and requesting organizations.

The blank establishes a partnership between the performing and requesting organizations.

Group of answer choices

Project management plan

Project statement of work

Project performance contract

Project charter

Flag question: Question 14Question 144 pts

A project charter is not considered to be a contract because there is no consideration or money promised by a project.

Group of answer choices

True

False

Flag question: Question 15Question 154 pts

A parametric estimate includes a

Group of answer choices

Pessimistic (most likely) and an optimistic value

Similar project

Mathematical model

Relative value

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Management

Authors: John A. Pearce II , Richard B. Robinson

14th International Edition

9814577375, 978-9814577373

More Books

Students also viewed these General Management questions