Flexible budgets, direct cost variances Terrigal Pots manufactures clay pots. All pots are the same size. Each unit requires the same amount of resources. The
Flexible budgets, direct cost variances
Terrigal Pots manufactures clay pots. All pots are the same size. Each unit requires the same amount of resources. The following information is from the static budget for 2015:
Expected production and sales 32 000 units Direct materials 48 000 kg Direct labour 16 000 hours Total fixed costs $75 000
Standard quantities, price and unit costs follow for direct materials and direct labour:
| Standard quantity | Standard price | Standard unit cost |
Direct materials | 1.5 kg | $2.5 per kg | $3.75 |
Direct labour | 0.5 hours | $25 per hour | $12.50 |
During 2015, actual number of units produced and sold was 35 000 units. Actual cost of direct materials used was $141 487.50, based on 57 750 kg purchased at $2.45 per kg. Direct labour hours actually used were 21 000 hours, at the rate of $21.50 per hour. As a result, actual direct labour costs were $451 500. Actual fixed costs were $85 000. There was no beginning or ending inventory.
Required:
- Prepare a flexible-budget-based variance analysis (similar to Table 11-3 p.426 textbook) for each of the three cost categories.
- Calculate price and efficiency variances for direct materials and direct labour.
- Comment on the results in parts 3 and 4 and provide a possible explanation for them.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started