Question

1 Approved Answer

Following successor relationshos are walable for a project. What is the duration of the project? table [ [ Activity 1 0 , Duration (

Following successor relationshos are walable for a project. What is the duration of the project?
\table[[Activity 10,Duration(days),Successors],[A,5,G],[B,12,C.D],[C,6,D.F],[D,8,E],[E,12,F],[F,3,]]
a.22 ders
b.26 days
c.40 days
d.45 dsys
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managing: A Competency-based Approach

Authors: Don Hellriegel

Eleventh Edition

0324421400, 978-0324421408

More Books

Students also viewed these General Management questions