For a given project, duration and resource requirements are given below Activity Duration (weeks) Machines Crew size (Men) 1-2 7 2 20 1-3 7 2
- For a given project, duration and resource requirements are given below
Activity Duration (weeks) Machines Crew size (Men)
1-2 7 2 20
1-3 7 2 20
2-3 8 3 30
2-4 6 4 30
3-6 9 2 20
4-5 3 2 20
5-6 5 2 20
Resources AVAILABILITY: (A) Machines 4 (B) Men 40
- Draw the network diagrm, identify the critical path assuming that there are no resource constraints.
- Draw the time scale network as per EST and level the resources
- Find the project completion time under the given resource constraint.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started