For a given project, duration and resource requirements are given below Activity Duration (weeks) Machines Crew size (Men) 1-2 7 2 20 1-3 7 2

  1. For a given project, duration and resource requirements are given below

Activity Duration (weeks) Machines Crew size (Men)

1-2 7 2 20

1-3 7 2 20

2-3 8 3 30

2-4 6 4 30

3-6 9 2 20

4-5 3 2 20

5-6 5 2 20

Resources AVAILABILITY: (A) Machines 4 (B) Men 40

  1. Draw the network diagrm, identify the critical path assuming that there are no resource constraints.
  2. Draw the time scale network as per EST and level the resources
  3. Find the project completion time under the given resource constraint.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

General Managers In Action Policies And Strategies

Authors: Francis Joseph Aguilar

2nd Edition

0195073673, 978-0195073676

More Books

Students also viewed these General Management questions