For a small manufacturing project consider the following : - Baseline contact value = $80,000 - Planned progress (as per schedule baseline ) = 40%

For a small manufacturing project consider the

following :

- Baseline contact value = $80,000

- Planned progress (as per schedule baseline ) = 40%

- Your Data Date @ 47.5% physical progress .

- Actual expenditure = $48,000

-

1- Calculate the required fund , assuming the same calculated projection of cost performance, that must be obtained for the remaining work (ETC)

2- Interpret schedule and cost performance for this contractor, consider KPIs = 0.90 is a Corporate target .

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Cost Management Strategies For Business Decisions

Authors: Ronald Hilton, Michael Maher, Frank Selto

4th Edition

0073526800, 9780073526805

Students also viewed these General Management questions