For one specific project, the estimated average time for the critical path is 120 days. The standard deviation along the critical path is 8. Please
For one specific project, the estimated average time for the critical path is 120 days. The standard deviation along the critical path is 8. Please choose the correct answer by using PERT analysis.
4. If the operation manager wants the project to be completed with 99% of probability, what is the completion time the manager needs to set?