For the data in the table attached, please evaluate the cost of the plan given in the table if an in-house regular hour is 10$,
For the data in the table attached, please evaluate the cost of the plan given in the table if an in-house regular hour is 10$, overtime hour is 15$, and a contract man-hour costs 25. In addition, every backlog man-hour delayed from period t to t + 1 costs 5. Develop an alternative competitive plan in which you can have instead of 5 skilled employees have a mixture of skill and unskilled. The hour of unskilled worker is 8$.