For the following table given below, find out the critical path and total duration for the project. (5+3=8 marks) AutoSave . Off) Final Exam-PCM130 -

For the following table given below, find out the critical path and total duration for the project. (5+3=8 marks)

image text in transcribed
AutoSave . Off) Final Exam-PCM130 - Protected View . Saved v Search Yaser Shaikh 8 X File Home Insert Draw Design Layout References Mailings Review View Help Comments Viewing Share i PROTECTED VIEW Be careful-files from the Internet can contain viruses. Unless you need to edit, it's safer to stay in Protected View. Enable Editing Q2. For the following table given below, find out the critical path and total duration for the project. (5+3=8 marks) Activity Immediate Time estimate Predecessors (days A 30 15 25 A 3 C 7 InTmon 1 D, 5 D, F 2 - - H, I 10 K G , J 8 03. For the following information available. answer the following questions: Page 1 of 2 56 of 149 words " Focus + 100% Type here to search 15 O w 270C ~ BENG 15:28 13-04-2023

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals of Management

Authors: Robbins, DeCenzo, Coulter

7th Edition

132996855, 0-13-610982-9 , 9780132996853, 978-0-13-61098, 978-0136109822

More Books

Students also viewed these General Management questions