For the following test marketing project at week 6: Use the % Complete column and determine PV and EV, calculate the cost, schedule, and time

For the following test marketing project at week 6:

Use the "% Complete" column and determine PV and EV, calculate the cost, schedule, and time variances. Also calculate the CPI, SPI, CSI, and the ETC and EAC. DO NOT ASSUME 50-50 PERCENTAGE COMPLETE RULE

image text in transcribed
Duration Activity Predecessors (weeks) Budget, $ Actual Cost, $ % Complete a: Build items 300 400 100 b: Supply stores 200 180 100 c: Create ad program LUNWN 250 300 100 d: Schedule ads 600 400 20 c: Check sale results b. c 400 200 20

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Management Text And Cases

Authors: Gregory Dess , Gerry McNamara , Alan Eisner , Steve Sauerwald

11th Edition

1264124325, 978-1264124329

More Books

Students also viewed these General Management questions