For the following test marketing project at week 6: Use the % Complete column and determine PV and EV, calculate the cost, schedule, and time
For the following test marketing project at week 6:
Use the "% Complete" column and determine PV and EV, calculate the cost, schedule, and time variances. Also calculate the CPI, SPI, CSI, and the ETC and EAC. DO NOT ASSUME 50-50 PERCENTAGE COMPLETE RULE
Duration Activity Predecessors (weeks) Budget, $ Actual Cost, $ % Complete a: Build items 300 400 100 b: Supply stores 200 180 100 c: Create ad program LUNWN 250 300 100 d: Schedule ads 600 400 20 c: Check sale results b. c 400 200 20Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started