Foster Generators operates plants in Cleveland, Ohio; Bedford, Indiana; and York, Pennsylvania. Production capacities over the next three - month planning period for one particular

Foster Generators operates plants in Cleveland, Ohio; Bedford, Indiana; and York, Pennsylvania. Production capacities over the next three-month planning period for one particular type of generator are as follows:
Origin Plant Three Months Production Capacity(Units)
1 Cleveland 5000
2 Bedford 6000
3 York 2500
Total 13,500
Management would like to determine how much of its production should be shipped from each plant to each distribution center. The objective is to determine the routes to be used and the quantity to be shipped via each route that will provide the minimum total transportation cost. The cost for each unit shipped on each route is given in the following table:
Complete the model formulation (objective function and constraints). Solve the model using Excel Solver.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Information Systems

Authors: James O'Brien

7th Edition

007293588X, 9780072935882

More Books

Students also viewed these General Management questions

Question

5. How can I help others in the network achieve their goals?

Answered: 1 week ago