From the following information, develop an AON project network. Note: Be sure to include a legend for your network solution. (i) Complete the forward and
From the following information, develop an AON project network. Note: Be sure to include a legend for your network solution. (i) Complete the forward and backward pass (ii) compute activity slack (iii) identify the critical path (iv) How many days will the project take? W W B Install drainage A 5 C Install power lines A 3 D Excavate site B,C 4 E Pourfoundation D 3