Question
George Jettson builds custom homes in Cincinnati. Jettson was approached not too long ago by a client about a potential project, and he submitted a
George Jettson builds custom homes in Cincinnati. Jettson was approached not too long ago by a client about a potential project, and he submitted a bid of $590,000, derived as follows:
Jettson adds a 25% profit margin to all jobs, computed on the basis of total cost. In this client's case the profit margin amounted to $118,000 ($472,000 25%), producing a bid price of $590,000. Assume that 60% of construction overhead is fixed. Required: A. Suppose that business is presently very slow, and the client countered with an offer on this home of $455,000. Should Jettson accept the client's offer? Why?
B. If Jettson has more business than he can handle, how much should he be willing to accept for the home? Why?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started