Question

1 Approved Answer

Giovani Romano is in charge of planning and coordinating the analytics work shop for SureAnalytics company. Listed below are the activity information ( time frames

Giovani Romano is in charge of planning and coordinating the analytics work shop for SureAnalytics company. Listed below are the activity information (time frames in weeks) for the project.
Activity Description Optimistic (a) Most Probable (m) Pessimistic (b)
A Plan event 234
B Select location 2.526
C Decide on speakers & vendors 444
D Prepare & mail brochures 246
E Update web site 1.52.53.5
F Final check with speakers & vendors 3.544.5
G Registration & hotel reservations 336
H Finalize last-minute details 255
Flag question: Question 1
Question 12 pts
Suppose the Critical Path is A-C-D-G-H, the Variance is (round it up to 2 decimal places)
Group of answer choices
1.05 weeks
0.48 weeks
1.53 weeks
1.50 weeks

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Brand Management Building Measuring and Managing Brand Equity

Authors: Kevin Lane Keller

4th edition

9780273779414, 132664259, 273779419, 978-0132664257

More Books

Students also viewed these General Management questions