Question

1 Approved Answer

Given a two-week Sprint for a team that has a velocity of 80 story points. It is now the end of day 6. The Daily

image text in transcribed

Given a two-week Sprint for a team that has a velocity of 80 story points. It is now the end of day 6. The Daily Scrum Meeting has reported 0, 6, 9,7,3, 12 story points done per respective day. Fill in the following table and draw the Sprint Burndown Chart. Day Story Points Story Points Done 2 3 4 5 7 10