Given the following information: ES for 3 - 6 is 1 5 days and ES for 4 - 6 is 3 2 days. The expected

Given the following information:
ES for 3-6 is 15 days and ES for 4-6 is 32 days.
The expected activity times are 22 days for 3-6,9 days for 4-6, and 7 days for 6-7.
(Hint: draw the network and complete a FW pass)
What is the ES for activity 6-7?
15
41
32
37
48
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Records And Information Management

Authors: William Saffady

4th Edition

1538152541, 978-1538152546

More Books

Students also viewed these General Management questions

Question

Explain how teams are assigned and formed

Answered: 1 week ago

Question

What is the background of the situation?

Answered: 1 week ago