Given the following information for a project, a) Draw the AON (Activity-On-Node) project network. b) Identify the critical path using backward and forward pass c)

Given the following information for a project,

a) Draw the AON (Activity-On-Node) project network.

b) Identify the critical path using backward and forward pass

c) Determine the total completion time of the project

Activity

Immediate Processor

Activity Time (days)

A

-

6

B

-

8

C

A, B

5

D

B

4

E

C

7

F

C, D

3

G

D

6

H

E, F, G

5

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managing Operations Across The Supply Chain

Authors: Morgan Swink, Steven Melnyk, Janet L. Hartley, M. Bixby Cooper

4th Edition

1260547639, 978-1260547634

More Books

Students also viewed these General Management questions

Question

Sell the quality of your brand or products.

Answered: 1 week ago