Given the following information in standard costing: Standard 11,900 hours at $3.60 Actual 11,800 hours at $3.80 What is the direct labor price variance? $2,360

Given the following information in standard costing:

Standard 11,900 hours at $3.60 Actual 11,800 hours at $3.80

What is the direct labor price variance?

$2,360 unfavorable.

$2,380 favorable.

$2,380 unfavorable.

$2,360 favorable.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Nessus Network Auditing

Authors: Russ Rogers

2nd Edition

1597492086, 978-1597492089

More Books

Students also viewed these Accounting questions

Question

List the components of the strategic management process. page 72

Answered: 1 week ago