Given the following information in standard costing: Standard 11,900 hours at $3.60 Actual 11,800 hours at $3.80 What is the direct labor price variance? $2,360
Given the following information in standard costing:
Standard 11,900 hours at $3.60 Actual 11,800 hours at $3.80
What is the direct labor price variance?
$2,360 unfavorable.
$2,380 favorable.
$2,380 unfavorable.
$2,360 favorable.