Question
Given the following network and activity time estimates, determine the earliest and latest activity times, slack, the expected project completion time and variance, and the
Given the following network and activity time estimates, determine the earliest and latest activity times, slack, the expected project completion time and variance, and the probability that the project will be completed in 28 days or less.
TIME ESTIMATES (DAYS) | |||||||
ACTIVITY | ACTIVITY PREDECESSOR | a | m | b | |||
A | - | 5 | 8 | 17 | |||
B | - | 7 | 10 | 13 | |||
C | A | 3 | 5 | 7 | |||
D | A | 1 | 3 | 5 | |||
E | B, C | 4 | 6 | 8 | |||
F | B, C | 3 | 3 | 3 | |||
G | D,E | 3 | 4 | 5 |
Step by Step Solution
3.55 Rating (155 Votes )
There are 3 Steps involved in it
Step: 1
Activity ACTIVITY before Optimistic a Most likely M Pessimistic b PERT Estimate a4Mb6 Dev...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get StartedRecommended Textbook for
Introduction to Management Science
Authors: Bernard W. Taylor
11th Edition
132751917, 978-0132751919
Students also viewed these General Management questions
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
View Answer in SolutionInn App