Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Given the following project being considered by a firm, draw the network diagram clearly. Find the Estimated Activity Time and Standard Deviation. Compute the ES
Given the following project being considered by a firm, draw the network diagram clearly. Find the "Estimated Activity Time" and "Standard Deviation". Compute the ES EF LS LF for all the activities. Compute the Slacks TS FS IS Identify the Critical Path after computing the time for all the paths.
Find the probability of completing the path with the longest expected duration by weeks; by weeks. By what time in weeks is management percent sure that this path will be completed? If the firm can complete the project for the funder within weeks, it will receive a bonus of $ But if the project delays beyond weeks, it must pay a penalty of $ due to lost opportunity. If the firm can choose whether or not to bid on this project, what should its decision be if the project is only a breakeven one normally?
Table Data for Qn #
tableActivity Title,,Time wecksActivityOptimistic,Most Likely,PessimisticB: Collect firm data,C: Analyze data,: Determine need,D: Determine profitability,E: Evaluate risk,F: Interview owners,G: Check references,H: Evaluate industry,I: Evaluate economy,J: Decide funding,
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started