Question
Given the following project to landscape a new building site: Activity Immediate Predecessor Activity Duration (days) Resource Used A 2 X, Y B A 2
Given the following project to landscape a new
building site:
Activity
Immediate
Predecessor
Activity
Duration
(days)
Resource
Used
A 2 X, Y
B A 2 X
C A 3 X
D B, C 4 X, Y
E D 3 W, X
F D 1 W, X, Y
G E, F 2 X, Y
(a) Draw a Gantt chart using MSP.
(b) Assuming a fi ve - day week, fi nd the critical path
and project duration in days.
(c) Given that each resource is assigned 100 percent
to each task, identify the resource constraints.
(d) Using the MSP default, level the resources and
determine the new project duration and critical
path.
(e) Identify what alternative solutions can be used
to shorten the project duration without overallocating
the resources.
PROBLEMS 20. Given the following project to landscape a new (c) Given that each resource is assigned 100 percent building site: to each task, identify the resource constraints (d) Using the MSP default, level the resources and Immediate ActivityPredecesso(days) Activitv DurationResourc determine the new project duration and critical path Se (e) Identify what alternative solutions can be used X, Y to shorten the project duration without overal- locating the resources. 21. Given the following project (all times are in days): B, C X, Y Acti- Prede Normal Normal Crash Crash vity cessor Time Cost Time Cost $503 $150 200 160 50 W, X, Y X, Y 40 2 706 20 30 805 50 4 603 E, F a, C (a) Draw a Gantt chart using MSP (b) Assuming a five-day week, find the critical path a, C 290 100 180 and project duration in days 7.53 x 10.18 inStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started