Question

1 Approved Answer

Given the following sets of information, please assess the progress of the project at the end of Day 7. Please calculate Cost Variance (CV), Cost

Given the following sets of information, please assess the progress of the project at the end of Day 7. Please calculate Cost Variance (CV), Cost Performance Index (CPI), Schedule Variance (SV) and Schedule Performance Index (SPI) based on the data given below. Table 1 shows the data for each project activity. Table 2 shows the schedule of the project and Table 3 presents the planned and actual progress as well as the actual cost of the project activities at the end of Day 7.

PLEASE CHECK BAC & COST in Table 1 BEFORE CALCULATING;

image text in transcribed

Table 1: Project activity data Activity A B D E F G Table 2: Project schedule Activity A B D D Predecessors A B B D E F G E F 2 3 4 5 E F G Table 3: Project progress data (Field Report at end of Day 7) Activity Actual Complete (%) A 100 B 100 33.33 50 0 0 0 Duration (Days) Y 2 3 3 2 1 1 1 1 Cost/Day ($00s) Z CO 3 7 9 1 3 9 3 Scheduled Complete (%) 100 100 66.67 100 0 0 0 7 BAC ($) =YxZ 600 2100 2700 200 300 900 300 Reporting Date 8 9 10 Actual Incurred Cost ($) 2000 1800 1200 1100 0 0 0 Table 1: Project activity data Activity A B D E F G Table 2: Project schedule Activity A B D D Predecessors A B B D E F G E F 2 3 4 5 E F G Table 3: Project progress data (Field Report at end of Day 7) Activity Actual Complete (%) A 100 B 100 33.33 50 0 0 0 Duration (Days) Y 2 3 3 2 1 1 1 1 Cost/Day ($00s) Z CO 3 7 9 1 3 9 3 Scheduled Complete (%) 100 100 66.67 100 0 0 0 7 BAC ($) =YxZ 600 2100 2700 200 300 900 300 Reporting Date 8 9 10 Actual Incurred Cost ($) 2000 1800 1200 1100 0 0 0

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financing California Real Estate Spanish Missions To Subprime Mortgages

Authors: Lynne P. Doti

1st Edition

184893601X, 978-1848936010

More Books

Students also viewed these Finance questions

Question

1. Where do these biases come from?

Answered: 1 week ago

Question

7. What decisions would you make as the city manager?

Answered: 1 week ago