Question

1 Approved Answer

Given the following tasks data for a project, table [ [ Task Label,Predecessor,Duration ( weeks ) ] , [ A , - , 5

Given the following tasks data for a project,
\table[[Task Label,Predecessor,Duration (weeks)],[A,-,5],[B,-,3],[C,-,4],[D,A,1],[E,B,2],[F,B,5],[G,B,9],[H,C,D,E,4],[I,F,2]]
a. Draw the CPM network (AON) diagram
I. Determine the earliest start and latest start, earliest finish and latest finish times for each task. Use the following format to draw the network diagram and to present your answers.
-Earliest start = maximum EF of immediate predecessors EF=ES+t
-Latest finish = minimum of latest start of following activities LS=LF-t
II. Identify the total slack, free slack, safety slack, and independent slack for each task.
III. Determine the critical path.
IV. Determine the minimum project completion time.
b. Draw the Gantt chart
I. Determine the project completion time.
II. Determine each task's total slack.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Understanding Management

Authors: Richard L Daft, Dorothy Marcic

6th Edition

9780324581782, 324581785, 978-0324568387

More Books

Students also viewed these General Management questions

Question

(a) f (0) = 0. lim lim

Answered: 1 week ago