Great Product, Ltd . has just received an order for 1 4 0 Whozats, which must be ready for delivery at the start of week
Great Product, Ltd has just received an order for Whozats, which must be ready for delivery at the start of week # An MRP planner has prepared the following table showing product structure, lead times orders are lotforlot and quantities on hand:
tableWHOZAT PARTS LIST,LEAD TIME,ON HANDWhozat week,Whatzat weeks,Wherezat week,
NB: A Whozat is composed of Whatzats A Whatzat is composed of Wherezats
How many Wherezats should be ordered?