Hany Marcos has been hired to complete the WBS for a small construction project. The duration of the task is 3 days and the work
Hany Marcos has been hired to complete the WBS for a small construction project. The duration of the task is 3 days and the work is calculated as 24 hours. Hany believes the task will take 2 days to complete and the project manager agreed to allow Hany 2 days to complete the work, but absolutely no more than 2 days. This is a ____________________ type of task. Change the required hours to 9 days. The new work recalculates to become ____________________.