Question
Here is the information that Emma has accumulated so far: The Capital Budgeting Projects She must choose one of the four capital budgeting projects listed
Here is the information that Emma has accumulated so far:
The Capital Budgeting Projects
She must choose one of the four capital budgeting projects listed below:
Table 1
t | A | B | C | D |
0 | (14,850,000) | (17,500,000) | (16,600,000) | (17,900,000) |
1 | 4,500,000 | 4,500,000 | 5,660,000 | 4,680,000 |
2 | 4,500,000 | 5,560,000 | 5,660,000 | 6,780,000 |
3 | 5,200,000 | 5,820,000 | 5,200,000 | 5,900,000 |
4 | 6,800,000 | 6,500,000 | 4,600,000 | 5,800,000 |
Risk | High | Average | Average | Low |
Table 1 shows the expected after-tax operating cash flows for each project. All projects are expected to have a 4 year life. The projects differ in size (the cost of the initial investment), and their cash flow patterns are different. They also differ in risk as indicated in the above table.
The capital budget is $20 million and the projects are mutually exclusive.
Capital Structures
Greenpower Ltd. has the following capital structure, which is considered to be optimal:
Debt | 30% |
Preferred Equity | 10% |
Common Equity | 60% |
| 100% |
Cost of Capital
Emma knows that in order to evaluate the projects she will have to determine the cost of capital for each of them. She has been given the following data, which he believes will be relevant to her task.
(1)The firms tax rate is 35%.
(2) Greenpower Ltd. has issued a 12% semi-annual coupon bond with 15 years term to maturity. The current trading price is $1,105.
(3) The firm has issued some preferred stock which pays an annual 10.5% dividend of $100 par value, and the current market price is $102.
(4) The firms stock is currently selling for $54 per share. Its last dividend (D0) was $2.80, and dividends are expected to grow at a constant rate of 7%. The current risk free return offered by Treasury security is 2.5%, and the market portfolios return is 10.40%. Greenpower Ltd. has a beta of 1.3. For the bond-yield-plus-risk-premium approach, the firm uses a risk premium of 2.5%.
(5) The firm adjusts its project WACC for risk by adding 2.0% to the overall WACC for high-risk projects and subtracting 2.1% for low-risk projects.
Emma knows that Greenpower Ltd. executives have favored IRR in the past for making their capital budgeting decisions. Her professor at Seattle U. said NPV was better than IRR. Her textbook says that MIRR is also better than IRR. She is the new kid on the block and must be prepared to defend her recommendations.
First, however, Emma must finish the analysis and write her report. To help begin, she has formulated the following questions:
- What is the firms cost of debt?
- What is the cost of preferred stock for Greenpower Ltd.?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started