Question
Hi, Can somebody help me to solve the questions. Use the following information to answer the next three questions. Estimated manufacturing overhead for the year
Hi,
Can somebody help me to solve the questions.
Use the following information to answer the next three questions.
Estimated manufacturing overhead for the year
$240,000
Actual manufacturing overhead for the year
$210,000
Estimated direct labour hours for the year
6,000
Actual direct labour hours for the year
5,000
The following information pertains to the month of October:
Job No. 73
Job No. 77
Job No. 79
Direct materials
$2,000
$2,500
$3,000
Direct labour
$3,500
$4,000
$7,500
Direct labour hours
160
200
300
1.The predetermined overhead rate per direct labour hour would be:
A.$35
B.$40
C.$42
D.$48
E.None of the above
2.Assume the predetermined overhead rate is $30 per direct labour hour. Overhead applied to Job No. 73 would be:
A.$4,800
B.$6,400
C.$10,500
D.$15,000
E.None of the above
3.Assume the predetermined overhead rate is $30 per direct labour hour. Overhead applied during the month would be:
A.$15,000
B.$19,800
C.$12,500
D.$42,300
E.None of the above
Use the following information to answer the next three questions.
Job No. 1
Job No. 2
Job. No. 3
Direct materials
$25,000
$18,000
$32,000
Direct labour
$40,000
$53,000
$64,000
Machine hours
1,000
800
1,200
A predetermined overhead rate of $20 per machine hour is used to apply overhead.
All three jobs were started during September. Job No. 2 and Job No. 3 were completed during the month and Job No. 3 was sold on September 20. There were no beginning inventory balances.
4.Ending work in process inventory for September would be:
A.$0
B.$65,000
C.$85,000
D.$172,000
E.None of the above
5.Ending finished goods inventory for September would be:
A.$71,000
B.$87,000
C.$167,000
D.$207,000
E.None of the above
6.Cost of goods sold for September would be:
A.$0
B.$88,000
C.$96,000
D.$120,000
E.None of the above
7.
9.Canberra Company uses a predetermined overhead rate to assign overhead to jobs. Because Canberra Company's production is machine dominated, overhead is applied on the basis of machine hours. The expected overhead for the year was $2.5 million, and the practical level of activity is 50,000 machine hours.
During the year, Canberra Company used 48,000 machine hours and incurred actual overhead costs of $2 million. Canberra Company also had the following balances of applied overhead in its accounts:
$
Work in Progress
460,000
Cost of Goods Sold
1,440,000
Finished Goods
500,000
The predetermined overhead rate for Canberra Company is:
A.$50.00 per machine hour
B.$52.08 per machine hour
C.$41.67 per machine hour
D.$52.00 per machine hour
E.None of the above
10.Broome Ltd Industries uses a job costing system. The following data are available for 2018:
Budgeted:
Overhead
$675,000
Machine hours
25,000
Direct labour hours
75,000
Actual:
Overhead
$681,000
Machine hours
25,050
Direct labour hours
75,700
Number of units
400,000
Overhead is applied on the basis of direct labour hours.
Was overhead over or underapplied and by how much?
A.$300 underapplied
B.$300 overapplied
C.$6,000 underapplied
D.$6,000 overapplied
E.None of the above
Use the following information pertaining to Hobart Ltd to answer the next two questions.
Hobart Limited maintains a job costing system. Manufacturing overhead is applied to jobs at a uniform, predetermined rate of $0.40 per direct labour dollar. The following information is provided.
Work in progress at 1 January:
Job No
Material
Labour
Overhead
104
$2,000
$3,000
$1,200
Transactions for the month of January were as follows:
i.
Expenses incurred:
$
Factory salaries - indirect
5,000
Plant depreciation
2,000
Maintenance of machines
2,000
ii.
Labour charges to jobs:
$
Job No. 104
14,000
Job No. 105
8,000
iii.
Raw materials issued:
$
Job No. 104
14,000
Job No. 105
14,000
iv.
Job No. 104 was the only one completed during the month of January.
11.What is the total cost of Job No. 104?
A.$28,000
B.$33,600
C.$39,800
D.$30,000
E.None of the above
12.What is the total cost of Job No. 105?
A.$22,000
B.$25,200
C.$31,000
D.None of the above
Use the following information to answer the next three questions.
Estimated manufacturing overhead for the year
$240,000
Actual manufacturing overhead for the year
$210,000
Estimated direct labour hours for the year
60,000
Actual direct labour hours for the year
50,000
The following information pertains to the month of October:
Job No. 73
Job No. 77
Job No. 79
Direct materials
$2,000
$2,500
$3,000
Direct labour
$3,500
$4,000
$7,500
Direct labour hours
160
200
300
Jobs 73 and 77 were completed during the year.
13.Overhead applied to Job No. 73 would be:
A.$672
B.$640
C.$560
D.None of the above
14.Cost of Job No. 77 is:
A.$7,300
B.$6,500
C.$6,000
D.None of the above
15.Closing Work In Process was:
A.$11,700
B.$10,500
C.$11,550
D.None of the above
16.
Job No. 1
Job No. 2
Job. No. 3
Direct materials
$25,000
$18,000
$32,000
Direct labour
$40,000
$53,000
$64,000
Machine hours
1,000
800
1,200
A predetermined overhead rate of $20 per machine hour is used to apply overhead.
All three jobs were started during September. Job No. 2 and Job No. 3 were completed during the month and Job No. 3 was sold on September 20. There were no beginning inventory balances.
16.Cost of goods sold for September would be:
A.$156,000
B.$97,200
C.$120,000
D.None of the above
Use the following information pertaining to Perth Ltd to answer the next three questions.
Perth Ltd has identified the following overhead costs and cost drivers for next year.
Overhead Item
Expected Cost
$
Cost Driver
Expected Quantity
Setup costs
50,000
Number of setups
250
Ordering costs
20,000
Number of orders
1,600
Maintenance
100,000
Machine hours
2,000
Power
10,000
Kilowatt hours
40,000
180,000
The following are two of the jobs completed during the year.
Job 1000
Job 1001
Direct materials
$750
$1,000
Direct labour
$700
$1,200
Units completed
100
160
Direct labour hours
50
80
Number of setups
1
4
Number of orders
4
5
Machines hours
20
25
Kilowatt hours
30
50
The company's normal activity is 2,000 direct labour hours.
17.If direct labour hours are used to assign overhead, the total cost of Job 1000 would be:
A.$5,200
B.$5,250
C.$5,700
D.$5,950
E.None of the above
18.If the number of setups is used to assign setup costs, the amount of setup costs assigned to Job 1000 would be:
A.$200
B.$250
C.$400
D.$420
E.None of the above
19.If the four activity-based cost drivers are used to allocate overhead costs, total overhead allocated to Job 1000 would be:
A.$1,207.50
B.$1,257.50
C.$1,383.25
D.$1,407.50
E.None of the above
Use the following information pertains to Brisbane Manufacturing Ltd to answer the next three questions.
Brisbane Manufacturing Ltd uses an activity-based cost system. The company produces Model A and Model D. Information relating to the two products is given below.
Model A
Model D
Units produced
10,000
20,000
Machine hours
4,000
5,000
Direct labour hours
7,000
8,000
Engineering labour (hours)
500
700
Setups
20
30
The following costs are reported:
$
Engineering
24,000
Setups
50,000
Machine-related overhead
72,000
20.The pool rate for engineering is:
A.$20
B.$25
C.$28.50
D.$34.29
E.None of the above
21.Setup costs assigned to Model A are:
A.$18,000
B.$20,000
C.$25,000
D.$30,000
E.None of the above
22.Machine-related overhead costs assigned to Model D are:
A.$40,000
B.$54,400
C.$56,000
D.$59,200
E.None of the above
Use the following information pertains to Melbourne Manufacturing Ltd to answer the next four questions.
Melbourne Manufacturing Ltd has four categories of overhead. The four categories and expected overhead costs for each category for next year are listed below.
$
Maintenance
30,000
Materials Handling
4,500
Setups
4,000
Inspection
15,000
53,500
Currently, overhead is applied using a predetermined overhead rate based upon budgeted direct labour hours. 10,000 direct labour hours are budgeted for next year.
The company has been asked to submit a bid for a proposed job. The plant manager feels that obtaining this job would result in new business in future years. Usually bids are based upon full manufacturing cost plus 15%.
Estimates for the proposed job are as follows:
Direct materials
$500
Direct labour (300 hours)
$1,500
Number of materials moves
2
Number of inspections
3
Number of setups
4
Number of machine hours
40
In the past, full manufacturing cost has been calculated by allocating overhead using a volume-based cost driver, direct labour hours. The plant manager has heard of a new way of applying overhead that uses cost pools and cost drivers.
Expected activity for the four activity-based cost drivers that would be used are:
Machine hours
2,500
Material moves
300
Setups
100
Quality inspections
500
23.If direct labour hours are used as the cost driver, the amount of overhead allocated to the proposed job would be:
A.$1,275
B.$1,350
C.$1,605
D.$1,800
E.None of the above
24.If direct labour hours are used as the cost driver, the total cost of the proposed job would be:
A.$3,800
B.$3,605
C.$2,850
D.$2,775
E.None of the above
25.If material moves are used to assign material handling costs, the amount of material handling costs allocated to the proposed job would be:
A.$10.00
B.$24.50
C.$28.25
D.$30.00
E.None of the above
26.If the number of inspections is used to assign inspection costs, the amount of inspection costs allocated to the proposed job would be:
A.$90
B.$150
C.$165
D.$450
E.None of the above
27.If the activity-based cost drivers are used to assign overhead, the total cost of the proposed job would be:
A.$2,160
B.$2,200
C.$2,760
D.$3,036
E.None of the above
28.Hobart Kitchens Ltd have decided to develop an activity-based costing system. Shown below is each activity, its cost and the activity driver used to assign these costs to products.
Expected
Cost
Expected Quantity
Activity
Cost
Driver
Process orders
$37 800
No. orders
1 500 orders
Make patterns
$140 000
No. items made
8 000 items
Carving
$248 000
No. hours taken
4 000 hours
Finishing
$186 200
No. items made
8 000 items
Under an activity-based costing system, what is the activity cost per unit of activity driver for making patterns?
A. $4.73
B. $10.00
C. $17.50
D. $21.50
E.None of the above
Use the following information pertains to Adelaide Ltd to answer the next four questions.
Adelaide Ltd is a manufacturer of a range of natural confectionary products. The following is a list of activities, costs and quantities of activity drivers for a number of activities that occur in the factory.
Activity
Expected
cost
Cost
driver
Expected Quantity
Measure ingredients
$7 000
batches
500 batches
Load machines
$9 200
No. batches
500 batches
Supervise mixing
$36 000
No. machine hours
4 500 MH
Pack into containers
$24 000
No. litres
600 000 litres
Load into freezers
$10 500
No. cartons
350 000 cartons
29.Under an activity-based costing system, what is the activity cost per unit of activity driver for measuring ingredients?
A. $12.90
B. $15.00
C. $13.80
D. $14.00
E.None of the above
30.Under an activity-based system, what is the activity cost per unit of activity division for packing into containers?
A. $0.06
B. $0.05
C. $0.02
D. $0.04
E. None of the above
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started