Hickory Company manufactures two products 15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all $597,000 of its manufacturing overhead to four cost pools. The following additional information is avallable for the company as a whole and for Products Y and Z : 8. Which of the four activities is a product level activity? Machining General factory Machine setups Product design Hickory Company manufactures two products 15,000 units of Product Y and 7.000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an actlvity-based costing (ABC) system that allocates all $597,000 of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z : Using the ABC system, how much total manufacturing overhead cost would be assigned to Product Y? (Round all interme diate colculations to 2 decimal places.) Hickory Company manufactures two products 15,000 units of Product Y and 7,000 units of Product Z. The company use a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all $597,000 of its manufacturing overhead to four cost pools. The following additional information available for the company as a whole and for Products Y and Z 10. Using the ABC system, how much total manufacturing overhead cost would be assigned to Product Z? Hickory Company manufactures two products 15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all $597,000 of its manufacturing overhead to four cost pools. The following additional information is. available for the company as a whole and for Products Y and Z : 11 Using the plantwide overhead rate, what percentage of the total overhead cost is allocated to Product Y and Product Z? (Round your "Percentage" answers to 2 decimal place.) Hickory Company manufactures two products 15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours, It is considering implementing an activity based costing (ABC) system that allocates all $597,000 of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z 12. Using the ABC system, what percentage of the Machining costs is assigned to Product Y and Product Z ? (Round your "Percentage" onswers to 2 decimal ploces.) Hickory Company manufactures two products 15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours, It is considering implementing an activity-based costing (ABC) system that allocates all $597,000 of its manufacturing overhead to four cost pools. The following additional information is: available for the company as a whole and for Products Y and Z 13. Using the ABC systemt, what percentage of Machine Selups cost hs assigned to Product Y and Product Z ? (Round your "Percentoge" onswers to 2 decimal places.) Hickory Company manufactures two products -15.000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all $597,000 of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z : 14. Using the ABC system, what percentage of the Product Design cost is assigned to Product Y and Product Z? Hickory Company manufactures two products 15,000 units of Product Y and 7.000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all $597,000 of its manufacturing overhead to four cost pools. The following additional information is avallable for the company as a whole and for Products Y and Z : 15. Using the ABC system, what percentage of the General Factory cost is assigned to Prgduct Y and Product Z ? (Round your "Percentoge" answers to 2 decimal place.)