Hickory Company manufactures two products14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct

Hickory Company manufactures two products14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all $748,800 of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z:

Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity
Machining Machine-hours $ 206,000 10,000 MHs
Machine setups Number of setups $ 145,600 260 setups
Product design Number of products $ 90,000 2 products
General factory Direct labor-hours $ 307,200 12,000 DLHs
Activity Measure Product Y Product Z
Machine-hours 7,600 2,400
Number of setups 50 210
Number of products 1 1
Direct labor-hours 8,600 3,400

Required:

1. What is the companys plantwide overhead rate?

2. Using the plantwide overhead rate, how much manufacturing overhead cost is allocated to Product Y and Product Z?

3. What is the activity rate for the Machining activity cost pool?

4. What is the activity rate for the Machine Setups activity cost pool?

5. What is the activity rate for the Product Design activity cost pool?

6. What is the activity rate for the General Factory activity cost pool?

7. Which of the four activities is a batch-level activity?

8. Which of the four activities is a product-level activity?

9. Using the ABC system, how much total manufacturing overhead cost is assigned to Product Y?

10. Using the ABC system, how much total manufacturing overhead cost is assigned to Product Z?

11. Using the plantwide overhead rate, what percentage of the total overhead cost is allocated to Product Y and Product Z?

12. Using the ABC system, what percentage of the Machining costs is assigned to Product Y and Product Z?

13. Using the ABC system, what percentage of Machine Setups cost is assigned to Product Y and Product Z?

14. Using the ABC system, what percentage of the Product Design cost is assigned to Product Y and Product Z?

15. Using the ABC system, what percentage of the General Factory cost is assigned to Product Y and Product Z?

Thank you so much!

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction to Managerial Accounting

Authors: Peter Brewer, Ray Garrison, Eric Noreen

7th edition

978-1259675539, 125967553X, 978-1259594168, 1259594165, 78025796, 978-0078025792

More Books

Students also viewed these Accounting questions

Question

=+b) Find the standard deviations.

Answered: 1 week ago