Question
1 Approved Answer
How do I make a critical path diagram for the below? Activity Dependencies Earliest Start (weeks) Earliest Finish (weeks) 1 Market Research and Vendor Selection
How do I make a critical path diagram for the below?
Activity | Dependencies | Earliest Start (weeks) | Earliest Finish (weeks) | |
1 | Market Research and Vendor Selection | 0 | 4 | |
2 | Contract Negotiation | 1 | 4 | 10 |
3 | Order and Delivery | 1,2 | 10 | 18 |
4 | Technical Evaluation and Vendor Selection | 1 | 0 | 5 |
5 | Purchase Order and Contracting | 4 | 5 | 12 |
6 | Delivery and Installation | 5 | 12 | 22 |
7 | Site Analysis and Selection | 0 | 6 | |
8 | Permitting and Regulatory Approval | 7 | 6 | 14 |
9 | Construction | 7,8 | 14 | 34 |
10 | Needs Assessment and Vendor Evaluation | 0 | 4 | |
11 | Software Development or Configuration | 1 | 4 | 16 |
12 | Integration and Testing | 11 | 16 | 24 |
13 | Request for Proposals (RFP) and Vendor Selection | 0 | 5 | |
14 | Contract Negotiation | 13 | 5 | 11 |
15 | Service Implementation and Training | 14 | 11 | 21 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started