How many of the following are potential causes of a direct labour quantity (efficiency) variance being unfavourable? i. A last minute change in suppliers causing
How many of the following are potential causes of a direct labour quantity (efficiency) variance being unfavourable?
i. A last minute change in suppliers causing the price to increase for direct materials ii. Outdated and faulty equipment prone to breakdowns during production iii. Purchase of poor quality materials iv. A new contract enforced by the union increasing wages for the production line workers
options:
| 2 |
| 0 |
| 1 |
| 3 |