Question
https://docs.google.com/spreadsheets/d/12um_RxcGltdgWGvVD56wLoeW3vk6m9LM/edit?usp=sharing&ouid=117626949194590888450&rtpof=true&sd=true Using a two-day lead time (all original values),what is the total cost if we increase the min and max by 15% each? A. $254,508
https://docs.google.com/spreadsheets/d/12um_RxcGltdgWGvVD56wLoeW3vk6m9LM/edit?usp=sharing&ouid=117626949194590888450&rtpof=true&sd=true
Using a two-day lead time (all original values),what is the total cost if we increase the min and max by 15% each?
A. | $254,508 | |
B. | $239,868 | |
C. | $527,679 | |
D. | $423,019 |
Using a two-day lead time (all original values), what amount will be ordered on day 95, assuming a min of 3,000and a max of 5,100?
A. | 2,389 | |
B. | 2,711 | |
C. | 2,990 | |
D. | 0 | |
E. | 2,769 |
Using a two-day lead time (all original values),what is the total holding cost assuming that a min and max of 2,900 and 4,400, respectively, are used?
A. | $95,613 | |
B. | $244,047 | |
C. | $115,083 | |
D. | $123,400 |
Using a two-day lead time (all original values), what is the optimal min and max to get the lowest total cost, rounded to the nearest increment of 50?
A. | Min=2,800 Max=4,200 | |
B. | Min=2,750 Max=4,200 | |
C. | Min=2,800 Max=4,150 | |
D. | Min=2,750 Max =4,150 |
Using a three-day lead time (all original values), what is the total cost with a min and max of 4,300and 5,800,respectively? (Round to the nearest whole number) _______________________
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started