Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Scenario A. A particular construction project has the following characteristics: Task Duration Predecessor(s) A 3 - B 6 - C 3 - D 5 A

Scenario A. A particular construction project has the following characteristics:

Task

Duration

Predecessor(s)

A

3

-

B

6

-

C

3

-

D

5

A

E

3

C

F

7

A

G

4

B, D, E

1. Determine the critical path.

2. Determine the expected duration of the project.

Scenario B. The budgeted cost to c.o.m.plete a particular project is $250,000. To date, the budgeted cost of work scheduled (planned Value) is $45,000, and the following work packages of the project have been c.o.mpleted or are in process:

Work Pkg.

Work Pkg. Budget

Reported % Complete

Actual Costs to Date

Planned Value

Earned Value

A

$15,000

100

$19,000

?

$15,000

B

11,000

100

14,000

?

11,000

C

14,000

50

7,000

?

7,000

D

20,000

10

2,000

?

2,000

Total

$60,000

$42,000

$45,000

$35,000

Now that tasks A and B are 100% c.omplete, and assuming that the work package achieved the technical/performance targets for these two work packages, how is the project doing?

3. What is the schedule variance? What does this result mean?

4. What is the cost variance? What does this result mean?

Scenario C. Take the data from scenario B and assume that the original schedule called for the project to be c.ompleted within seven months and that the performance for the remainder of the project is similar to the performance to date.

5. What is the estimated total cost at completion?

6. What is the estimated completion date?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managing Information Technology

Authors: Carol Brown, Daniel DeHayes, Jeffrey Hoffer, Wainright Marti

7th Edition

132146320, 978-0132146326

More Books

Students also viewed these General Management questions

Question

Explain one area of concern or criticism of natural law theory.

Answered: 1 week ago