Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Hyde Restorations rebuilds factory facilities. It employs 1 3 0 full - time workers at $ 2 5 per hour. Despite operating at capacity, last

Hyde Restorations rebuilds factory facilities. It employs 130 full-time workers at $25 per hour. Despite operating at capacity, last years performance was a great disappointment to the managers. In total, nine jobs were accepted and completed, incurring the following total costs:
Direct materials $ 1,222,200
Direct labor 4,560,000
Manufacturing overhead 1,167,360
Of the $1,167,360 manufacturing overhead, 25 percent was variable overhead and 75 percent was fixed.
This year, Hyde expects to operate at the same activity level as last year, and overhead costs and the wage rate are not expected to change. For the first quarter of this year, Hyde Restorations completed two jobs and was beginning the third (Job 13). The costs incurred follow:
Direct Materials Direct Labor
Job 11 $ 179,560 $ 618,500
Job 12122,100396,500
Job 13123,400253,000
Total manufacturing overhead 326,640
Total marketing and administrative costs 158,000
You are a consultant associated with Conway & Company, which has been hired by Hyde to analyze the profitability issue. The managing partner on the engagement has reviewed the accounts at Hyde and suggests you start by classifying the overhead into fixed and variable components for each of the jobs. With the help of the Hyde supervisors on each of the jobs, you arrive at the following split.
Actual Manufacturing Overhead
Variable Fixed
Job 11 $ 37,080 $ 126,000
Job 1234,200107,040
Job 136,72021,600
$ 78,000 $ 254,640
In the first quarter of this year, 30 percent of marketing and administrative cost was variable and 70 percent was fixed. You are told that Jobs 11 and 12 were sold for $1,114,000 and $714,000, respectively. All over- or underapplied overhead for the quarter is written off to Cost of Goods Sold.
Required:
Present in T-accounts the actual manufacturing cost flows for the three jobs in the first quarter of this year.
Using last year's overhead costs and direct labor-hours as this year's estimate, calculate predetermined overhead rates per direct labor-hour for variable and fixed overhead.
Present in T-accounts the normal manufacturing cost flows for the three jobs in the first quarter of this year. Use the overhead rates derived in requirement (b).
Calculate operating profit (loss) for the first quarter of this year under actual and normal costing systems.
Hyde Restorations rebuilds factory facilities. It employs 130 full-time workers at $25 per hour. Despite operating at capacity, last year's
performance was a great disappointment to the managers. In total, nine jobs were accepted and completed, incurring the following
total costs:
Of the $1,167,360 manufacturing overhead, 25 percent was variable overhead and 75 percent was fixed.
This year, Hyde expects to operate at the same activity level as last year, and overhead costs and the wage rate are not expected to
change. For the first quarter of this year, Hyde Restorations completed two jobs and was beginning the third (Job 13). The costs
incurred follow:
You are a consultant associated with Conway & Company, which has been hired by Hyde to analyze the profitability issue. The
managing partner on the engagement has reviewed the accounts at Hyde and suggests you start by classifying the overhead into
fixed and variable components for each of the jobs. With the help of the Hyde supervisors on each of the jobs, you arrive at the
following split.
In the first quarter of this year, 30 percent of marketing and administrative cost was variable and 70 percent was fixed. You are told that
Jobs 11 and 12 were sold for $1,114,000 and $714,000, respectively. All over- or underapplied overhead for the quarter is written off to
Cost of Goods Sold.
Required:
a. Present in T-accounts the actual manufacturing cost flows for the three jobs in the first quarter of this year.
b. Using last year's overhead costs and direct labor-hours as this year's estimate, calculate predetermined overhead rates per direct
labor-hour for variable and fixed overhead.
c. Present in T-accounts the normal manufacturing cost flows for the three jobs in the first quarter of this year. Use the overhead rates
derived in requirement (b).
d. Calculate operating profit (loss) for the first quarter of this year under actual and normal costing systems.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting And Causal Effects Econometric Challenges

Authors: Douglas A Schroeder

1st Edition

1441972242, 9781441972248

More Books

Students also viewed these Accounting questions

Question

Describe several uses for a position description.

Answered: 1 week ago