Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

I need help to get the following : Project Professional File .mpp Cost Overview Report Resource Overview Report Critical Task Report GANTT Chart You were

image text in transcribedimage text in transcribedimage text in transcribed

I need help to get the following :

Project Professional File .mpp

Cost Overview Report

Resource Overview Report

Critical Task Report

GANTT Chart

You were asked to schedule the entire project in Project Professional based on the tasks and resources listed below: The project starts on February 20th, 2023. EMPower Inc. has a unique work schedule as the factory is open from 7am to 7pm on Monday to Thursday. Fridays, Saturdays, and Sundays are off. Lunch break is from 12 to 1pm. You were given access to an unused section of the factory which needs to be prepared. All of the tools and equipment is already here, but it needs to be moved and installed. The fellow Project Manager experienced in this type of project gave you a list of tasks that you need to accomplish to achieve your milestones. Milestone: Phase I - Setun (Fixed Resources: You (PM)I Additionally, you need to get 3rd party certification for your load sensor. The first step is to receive Approval for Testing before the Phase I milestone. The application cost is $1650. Milestone Phase I Completed after Tasks 6&9 are completed. Milestone: Phase II - Manufacturing \& Testing (Fixed Resources: You (PM)) Phase II Completed after drawings are released. Milestone: Phase III - Final Review and Product Release (Fixed Resources: You (PM)) Phase III Completed atter product release. You were assigned to work with the following team: - You were given 2 technicians to help you with general tasks, but John Smith is your primary resource, and Jack Murray can be only assigned if both technicians are needed, or John is overallocated as overtime for technicians for this project is not allowed. (Over-times will be only allowed if there is no other way to assign technicians, but they need to be minimized) - All other resources can be overallocated as needed. - Mary Johnson will be helping you with some tasks, and you should be assigned to every task on the schedule as you are not going to be as involved as others in most of the tasks, but you will be tracking progress - The cost of material for each load cell is $44. - Shipping of Material is $1500 - 3rd Part Certification Application fee is $1650. - Shipping of load cells to 3Rd Part Reviewer is $240. Calendar Constraints: - After reviewing the project scope, the Director of Engineering would like to have a bi-weekly team meeting with the entire team two times a month on Thursdays. - 3rd Party Reviewer would like to schedule a factory tour and inspection for the first week of February. It will take a full day and no other activities should be planned during this time. - EMPower Inc. celebrates its 25th Anniversary and invites all of the employees for the anniversary party which is scheduled for March 17th,2023 from 1pm to 7pm, and no other activities can be scheduled during this time. You were asked to schedule the entire project in Project Professional based on the tasks and resources listed below: The project starts on February 20th, 2023. EMPower Inc. has a unique work schedule as the factory is open from 7am to 7pm on Monday to Thursday. Fridays, Saturdays, and Sundays are off. Lunch break is from 12 to 1pm. You were given access to an unused section of the factory which needs to be prepared. All of the tools and equipment is already here, but it needs to be moved and installed. The fellow Project Manager experienced in this type of project gave you a list of tasks that you need to accomplish to achieve your milestones. Milestone: Phase I - Setun (Fixed Resources: You (PM)I Additionally, you need to get 3rd party certification for your load sensor. The first step is to receive Approval for Testing before the Phase I milestone. The application cost is $1650. Milestone Phase I Completed after Tasks 6&9 are completed. Milestone: Phase II - Manufacturing \& Testing (Fixed Resources: You (PM)) Phase II Completed after drawings are released. Milestone: Phase III - Final Review and Product Release (Fixed Resources: You (PM)) Phase III Completed atter product release. You were assigned to work with the following team: - You were given 2 technicians to help you with general tasks, but John Smith is your primary resource, and Jack Murray can be only assigned if both technicians are needed, or John is overallocated as overtime for technicians for this project is not allowed. (Over-times will be only allowed if there is no other way to assign technicians, but they need to be minimized) - All other resources can be overallocated as needed. - Mary Johnson will be helping you with some tasks, and you should be assigned to every task on the schedule as you are not going to be as involved as others in most of the tasks, but you will be tracking progress - The cost of material for each load cell is $44. - Shipping of Material is $1500 - 3rd Part Certification Application fee is $1650. - Shipping of load cells to 3Rd Part Reviewer is $240. Calendar Constraints: - After reviewing the project scope, the Director of Engineering would like to have a bi-weekly team meeting with the entire team two times a month on Thursdays. - 3rd Party Reviewer would like to schedule a factory tour and inspection for the first week of February. It will take a full day and no other activities should be planned during this time. - EMPower Inc. celebrates its 25th Anniversary and invites all of the employees for the anniversary party which is scheduled for March 17th,2023 from 1pm to 7pm, and no other activities can be scheduled during this time

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Audit Analysis Part 1 Facts Of Auditing

Authors: Dr. L. KAILASAM

1st Edition

1670149455, 978-1670149459

More Books

Students also viewed these Accounting questions