I need to make WBS, network diagram and contingency plan for Organizing a one-day office tournament. The subject of the Project Execution Plan is a
I need to make WBS, network diagram and contingency plan for Organizing a one-day office tournament.
The subject of the Project Execution Plan is a project of the student's own choosing.Students will not physically carry out a project but will use the ideas to develop a project plan and create a status report.Projects may vary widely and may include such areas as construction of a vacation home, installation of a LAN network, starting a new business, organizing a charity event, a marketing campaign, organizing a sports tournament, filming a movie, leading an expedition, and developing a new product.The projects may be the students' own work in the past or something they anticipate working on in the future or simply a factitious product.The key is that the project provides a vehicle for demonstrating mastery of course concepts. Students will begin work in earnest in Unit 7 with their submission of a project scope statement and a project network (PERT) diagram, for which feedback, but not a separate grade, will be provided.
Instructions
- Using the style and requirements described in course readings, prepare a document that contains two items: a statement of the project scope, and a project network diagram (PERT) that will allow your professor to determine whether your proposed project is both appropriate and achievable.
Answer completed half****
Main objective is to organize successful One-day cricket tournament for J&J ltd.
Deliverables
- Podium for speech to be given by CEO and MD
- Organize healthy food supply
- Sitting arrangement in shade.
- Quality cricket equipment
Technical requirements
- Foot mikes on podium for best interaction possible.
- Arranging lights and emergency service on ground and for podium.
Assigning duties to at least two technicians.
Milestones
- Permission from owner of ground a week before the tournament. 23rd august august
- Preparing ground 4 days before the day. 26th august
- Preparing podium and last minute arrangements a day before the match. 29th august
- Arrange food beverage on 30th .
Expulsions and limits
Permit to play on ground is till 8pm only, prize distribution should be done by 7.30pm.
Cricket official equipment will be taken on rent and it is also to be returned by 8.30pm of 30th august.
Technicians will have to pick lights, fans and other electronic stuff by 8'O clock of evening. There tournament should be started on time and time management should be done.
Priority Establishment
Time
Performance
Cost
constrain
enhance
accept
Time for the project is fixed along with the date because ground needs to be evacuated by 8pm of 30th august. Performance of project can be enhanced. Arrangements can be made of high quality and requirement assistance can be taken from management and necessary developments can be done before the tournaments.
Work Breakdown structure
Activities of the tournament will be broken down into simple work tasks. First planning will be done then budgeting of equipment and every other expense. Fee of match, referee, rented equipment, food, ground and every miscellaneous item will be included in budgeting as far possible. Then teams will be asked to report all activities such as injuries. Then notice to employees will be sent to participate in tournament. Approval of tournament will take place and 30th august will be finalized. Technicians and podium organizers will be informed. Food will be ordered and cricket kits will be rented. Prizes will be bought and this whole task process will be monitored by project manager.
Estimation of the cost
Rent of ground = $500 CAD
2 Technician paid= $ 14 per hour ( Assuming they work for 15 hours during, before and after the tournament) = 14*15*2= 420$
Cricket kits(Rental)= 200$
Total duration is set to 15 hours. As it takes time to set the instruments before match, however if they need assistance then office technicians can help them.
Food and beverages
Breakfast = 100$ in total
Milk 5 litre = 25$
Total players = 11+ 2 subs= 13 *4 teams= 52
total employees = 120
Estimated gathering= 140
Milk will be only for players and meals will be provided to players by local restaurant who wanted to sponsor the meal in exchange for their advertisement to be presented during the tournament. CEO and MD will be given their special meal.
Rough total cost of food and beverages = 400$
Water=400 litre =200$ for tank
Total expected cost= 200+400+ 200+420+500 = 1720$
Budget will be set for 2000$
Task
Start date
End date
Assigned to
Progress
Ground permission
23rd august
24-25 august
John
-
Pitch making
26 August
26august
Kent & Chris
-
Equipment On rent
28 August
30th august
Kent & Chris
-
Jersey design
26 August
26 August
Kent & Chris
Printing
27 August
28 August
Local T-SHIRT printers
Notice to employees
25 August
-------
Kristine
Podium preparation
29 august
29 august
Technicians & Martha
Food beverages
30th august
----
Bart
Drinking Water tank
29th august
---
Bart
Technicians
26 august
30th august
Martha
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started