Question

1 Approved Answer

I ONLY NEED HELP WITH 1A of the following question: Flexible Budgeting and Variance Analysis I Love My Chocolate Company makes dark chocolate and light

I ONLY NEED HELP WITH 1A of the following question:

Flexible Budgeting and Variance Analysis

I Love My Chocolate Company makes dark chocolate and light chocolate. Both products require cocoa and sugar. The following planning information has been made available:

Standard Amount per Case
Dark Chocolate Light Chocolate Standard Price per Pound
Cocoa 12 lbs. 8 lbs. $7.25
Sugar 10 lbs. 14 lbs. 1.40
Standard labor time 0.50 hr. 0.60 hr.

Dark Chocolate Light Chocolate
Planned production 4,700 cases 11,000 cases
Standard labor rate $15.50 per hr. $15.50 per hr.

I Love My Chocolate Company does not expect there to be any beginning or ending inventories of cocoa or sugar. At the end of the budget year, I Love My Chocolate Company had the following actual results:

Dark Chocolate Light Chocolate
Actual production (cases) 5,000 10,000
Actual Price per Pound Actual Pounds Purchased and Used
Cocoa $7.33 140,300
Sugar 1.35 188,000
Actual Labor Rate Actual Labor Hours Used
Dark chocolate $15.25 per hr. 2,360
Light chocolate 15.80 per hr. 6,120

Required:

1. Prepare the following variance analyses for both chocolates and the total, based on the actual results and production levels at the end of the budget year: Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.

Direct materials price variance, direct materials quantity variance, and total variance.

Direct labor rate variance, direct labor time variance, and total variance.

a. Direct materials price variance $ Unfavorable
Direct materials quantity variance $ Favorable
Total direct materials cost variance $ Unfavorable
b. Direct labor rate variance $1,246 Unfavorable
Direct labor time variance -$310 Favorable
Total direct labor cost variance $936 Unfavorable

2. The variance analyses should be based on the standard amounts at actual volumes. The budget must flex with the volume changes. If the actual volume is different from the planned volume, as it was in this case, then the budget used for performance evaluation should reflect the change in direct materials and direct labor that will be required for the actual production. In this way, spending from volume changes can be separated from efficiency and price variances.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Will You Be My Internal Audit Manager

Authors: Benito Gross

1st Edition

B09774C8CK, 979-8521636563

More Books

Students also viewed these Accounting questions