ID Activity Predecessors Late a (weeks) m b (weeks) Start Variance (weeks) A Define 0 2 Requirements 4 6 (b-a) 2/36 B Design A 4
ID Activity Predecessors Late a (weeks) m b (weeks) Start Variance (weeks) A Define 0 2 Requirements 4 6 (b-a) 2/36 B Design A 4 4 Application 6 8 C Draft User A 10 4 Manual 6 D Prepare A 6 6 10 Code E Test Code B.C 10 2 W A F Correct Code E,D 12 3 4 What is the risk of not delivering this project in 18 weeks