Question

1 Approved Answer

Question 1: Critical Path Method. Provide manual answer. Do not use Excel or MS Project. Submit pdf file. Below is information about a project to

Question 1:Critical Path Method. Provide manual answer. Do not use Excel or MS Project.

Submit pdf file.

Below is information about a project to implement a new manufacturing cell to assemble personal digital assistant devices.

ACTIVITY

DURATION

PREDECESSORS

ES

EF

LS

LF

TOTAL SLACK

A. Design Process Requirements

2

---

B. Benchmark Competitors Processes

4

A

C. Prepare Benchmark Report

1

B

D. Design Process and Layout

2

A

E. Finalize design and setup manf. Cell

2

C, D

F. Select and train operators

1

D

G. Pilot test new process

2

E, F

H. Finalize process design

1

G

1.Draw a network diagram.

2.Identify the ES, EF, LS, LF and slack times in the table using the critical path method.

3.During the initial stages of the project, a new set of requirements were discovered that would extend the process and layout design activity from 2 to 6 months. The operations group which initiated these requirement changes argues that they would not impact the project duration. Is this true? Justify your answer.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Management

Authors: Richard Lynch

8th Edition

1292211407, 978-1292211404

More Books

Students also viewed these General Management questions