Question
1 Approved Answer
Identify predecessors for each of your activities. Then, employ the network diagram and calculate the schedule duration using the forward and backward pass methods. Provide
Identify predecessors for each of your activities. Then, employ the network diagram and calculate the schedule duration using the forward and backward pass methods.
Provide in excel format.
Number | Activity | O | P | M | WA |
1 | Permits | 48 | 120 | 72 | 76 |
2 | Source Tiny Home components | 24 | 72 | 36 | 40.6 |
3 | Access & Logs | 12 | 24 | 20 | 19.3 |
4 | Leveling | 18 | 36 | 24 | 25 |
5 | Frame floors | 8 | 16 | 12 | 12 |
6 | Frame walls | 8 | 16 | 12 | 12 |
7 | Move in large items | 4 | 12 | 8 | 8 |
8 | Plan layout | 12 | 24 | 16 | 16.6 |
9 | Apply glue to studs | 3 | 9 | 5 | 5.3 |
10 | Check window dimensions | 5 | 12 | 8 | 8.1 |
11 | Install windows | 12 | 24 | 16 | 16.6 |
12 | Frame roof | 36 | 72 | 50 | 50.6 |
13 | Plan roof layout | 3 | 9 | 5 | 5.3 |
14 | Frame doorway | 3 | 9 | 5 | 5.3 |
15 | Paint sidings | 4 | 12 | 7 | 7.3 |
16 | Outside trim work | 4 | 12 | 7 | 7.3 |
17 | Rough Plumbing | 36 | 120 | 72 | 74 |
18 | Rough Electrical | 48 | 72 | 50 | 53.3 |
19 | Rough gas | 48 | 72 | 50 | 53.3 |
20 | Rough HVAC | 48 | 72 | 50 | 53.3 |
21 | Insulate | 24 | 36 | 30 | 30 |
22 | Install flooring | 12 | 24 | 18 | 18 |
23 | Design kitchen layout | 6 | 12 | 8 | 8.3 |
24 | Finish and test all HVAC, electrical and gas | 3 | 9 | 5 | 5.3 |
25 | Clean up debris | 3 | 9 | 5 | 5.3 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started