Identify predecessors for each of your activities. Then, employ the network diagram and calculate the schedule duration using the forward and backward pass methods. Provide

Identify predecessors for each of your activities. Then, employ the network diagram and calculate the schedule duration using the forward and backward pass methods.

Provide in excel format.

Number Activity O P M WA
1 Permits 48 120 72 76
2 Source Tiny Home components 24 72 36 40.6
3 Access & Logs 12 24 20 19.3
4 Leveling 18 36 24 25
5 Frame floors 8 16 12 12
6 Frame walls 8 16 12 12
7 Move in large items 4 12 8 8
8 Plan layout 12 24 16 16.6
9 Apply glue to studs 3 9 5 5.3
10 Check window dimensions 5 12 8 8.1
11 Install windows 12 24 16 16.6
12 Frame roof 36 72 50 50.6
13 Plan roof layout 3 9 5 5.3
14 Frame doorway 3 9 5 5.3
15 Paint sidings 4 12 7 7.3
16 Outside trim work 4 12 7 7.3
17 Rough Plumbing 36 120 72 74
18 Rough Electrical 48 72 50 53.3
19 Rough gas 48 72 50 53.3
20 Rough HVAC 48 72 50 53.3
21 Insulate 24 36 30 30
22 Install flooring 12 24 18 18
23 Design kitchen layout 6 12 8 8.3
24 Finish and test all HVAC, electrical and gas 3 9 5 5.3
25 Clean up debris 3 9 5 5.3

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Management Text And Cases

Authors: Gregory Dess , Gerry McNamara , Alan Eisner , Steve Sauerwald

11th Edition

1264124325, 978-1264124329

More Books

Students also viewed these General Management questions