Identify which of the following statements about a work breakdown structure ( WBS ) is false. Question 2 2 Answer a . As a rule

Identify which of the following statements about a work breakdown structure (WBS) is false.
Question 22 Answer
a.
As a rule of thumb, there are often between 2 and 20 items in a WBS division (stage).
b.
The goal of the WBS is to reach an activity level that is associated with an individual job and individual responsibility.
c.
The WBS should be action (output) oriented.
d.
The WBS depicts the precedence relationships among the project tasks just like a network diagram.
e.
The WBS may be useful in the budget preparation process.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Understanding Management

Authors: Richard L Daft, Dorothy Marcic

6th Edition

ISBN: 9780324581782, 324581785, 978-0324568387

More Books

Students also viewed these General Management questions