If activity A has an early start of 10, an early finish of 16, and a late start of 12, what is the total float

If activity A has an early start of 10, an early finish of 16, and a late start of 12, what is the total float of the activity?

a.

4

b.

6

c.

2

d.

0

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Linear Algebra A Modern Introduction

Authors: David Poole

3rd edition

9781133169574 , 978-0538735452

More Books

Students also viewed these General Management questions

Question

Explain clearly

Answered: 1 week ago

Question

1. Effort is important.

Answered: 1 week ago