if making a bag uses 7 kilograms of wood and 4 meters of leather. two employees spend 21 hours making one bag. After the bag
if making a bag uses 7 kilograms of wood and 4 meters of leather. two employees spend 21 hours making one bag. After the bag is made it is cleaned by a power cleaner for half an hour.
what is the cost accounting of making one bag with the following details:
1kg of wood = $35
1 meter of leather= %150
cost rate of power cleaner per hour= $21
wage per hour= 15$