If the materials price variance is $600 F and the materials quantity and labour variances are each $450 U, what is the total materials variance?
If the materials price variance is $600 F and the materials quantity and labour variances are each $450 U, what is the total materials variance? a. $450 U b. $300 U c. $1,050 U d. $150 F e. $600 F