If the optimistic estimate for a task is 12 days, pessimistic is 18 days and the most likely is 14 days what is the
If the optimistic estimate for a task is 12 days, pessimistic is 18 days and the most likely is 14 days what is the PERT estimatg? O a 171/3days O b. 141/3 days Oc 16 2/3 days O d. 15 2/3 days
Step by Step Solution
3.37 Rating (156 Votes )
There are 3 Steps involved in it
Step: 1
14 days to optimistic time 12 days t...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get StartedRecommended Textbook for
Project management the managerial process
Authors: Eric W Larson, Clifford F. Gray
5th edition
73403342, 978-0073403342
Students also viewed these Civil Engineering questions
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
View Answer in SolutionInn App