Question

1 Approved Answer

If the optimistic estimate for a task is 12 days, pessimistic is 18 days and the most likely is 14 days what is the

image

If the optimistic estimate for a task is 12 days, pessimistic is 18 days and the most likely is 14 days what is the PERT estimatg? O a 171/3days O b. 141/3 days Oc 16 2/3 days O d. 15 2/3 days

Step by Step Solution

3.37 Rating (156 Votes )

There are 3 Steps involved in it

Step: 1

14 days to optimistic time 12 days t... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project management the managerial process

Authors: Eric W Larson, Clifford F. Gray

5th edition

73403342, 978-0073403342

More Books

Students also viewed these Civil Engineering questions

Question

What are the steps in negotiations?

Answered: 1 week ago

Question

How do the building blocks of AON and AOA differ?

Answered: 1 week ago