If Toyota Motor Company receives an order on May 2, begins production on May 15, and ships the order on May 17 immediately following production,
If Toyota Motor Company receives an order on May 2, begins production on May 15, and ships the order on May 17 immediately following production, then what is the manufacturing cycle efficiency (MCE) ratio? Manufacturing cycle efficiency (MCE) ratio 18.75 If customer demand is 208,000 units per month, and available manufacturing capacity is 13,500 hours per week, what is the Takt time for this firm? (Round your answer to 2 decimal places.) Takt time hour/unit