Imagine that youre now in time period 17. Activity 4-5 is now complete as scheduled, and Activity 3-6 has also just completed, two periods ahead

Imagine that youre now in time period 17. Activity 4-5 is now complete as scheduled, and Activity 3-6 has also just completed, two periods ahead of schedule. Imagine that Resource A cost $6,000 for each period it was active on Activity 3-6: 5 periods, not the 7 periods at $5,000 per period expected. You are now ahead.

image text in transcribed

1. What is the new forecasted total cost at completion using the Earned Value Method?

2. What is the new forecasted total cost at completion using the CPI method?

5 - 1-2 1-4 3-6 5-6 Resource Type 2-3 - 4-5 0 1 2 3 4 5 6 7 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 Jan 16 Sept 16 Nov 16 Dec 16 Jan 17 May 17 July 17 Aug April 18 5 - 1-2 1-4 3-6 5-6 Resource Type 2-3 - 4-5 0 1 2 3 4 5 6 7 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 Jan 16 Sept 16 Nov 16 Dec 16 Jan 17 May 17 July 17 Aug April 18

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction To Industrial Energy Efficiency Energy Auditing Energy Management And Policy Issues

Authors: Patrik Thollander, Magnus Karlsson, Patrik Rohdin, Johan Wollin, Jakob Rosenqvist

1st Edition

0128172479, 978-0128172476

More Books

Students also viewed these Accounting questions

Question

Decision Making in Groups Leadership in Meetings

Answered: 1 week ago