In 2016, Omega Construction began work on a contract with a price of $850,000 and estimated costs of $595,000. Data for each year of the
In 2016, Omega Construction began work on a contract with a price of $850,000 and estimated costs of $595,000. Data for each year of the contract are as follows:
2016 2017 2018
Costs incurred during the year $238,000$319,600$105,000
Estimated costs to complete357,000139,400-0-
Partial billings 260,000210,000380,000
Collections 240,000200,000410,000
21) Assuming the performance obligation is satisfied over time, what would be the balance in
Construction in Progress at the end of 2017?
A) $557,600
B) $659,600
C) $680,000
D) $782,000
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started