In 2021, the Westgate Construction company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in

In 2021, the Westgate Construction company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows.

2018 2019 2020
Cost incurred during the year $ 2,044,000 $ 2,628,000 $ 2,890,800
Estimated costs to complete as of year-end 5,256,000 2,628,000 0
Billings during the year 2,170,000 2,502,000 5,328,000
Cash collections during the year 1,885,000 2,600,000 5,515,000

5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.)

2021 2022 2023
Costs incurred during the year $ 2,044,000 $ 3,885,000 $ 3,285,000
Estimated costs to complete as of year-end 5,256,000 3,185,000 0

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals Of Entrepreneurial Finance

Authors: Marco Da Rin, Thomas Hellmann

8th Edition

0199744750, 9780199744756

More Books

Students also viewed these Accounting questions